Change the Control Node
Caution | The best method to change the control node is to disable clustering on the control node, wait for a new control election, and then re-enable clustering. If you must specify the exact unit you want to become the control node, use the procedure in this section. Note that for centralized features, if you force a control node change using either method, then all connections are dropped, and you have to re-establish the connections on the new control node. |
To change the control node, perform the following steps.
Procedure
Step 1 | Open the Cluster Status dialog box by choosing More () > Cluster Live Status. |
Step 2 | For the unit you want to become the control unit, choose More () > Change Role to Control. |
Step 3 | You are prompted to confirm the role change. Check the checkbox, and click OK. |